| DOL Home > OALJ > Davis-Bacon Act/Service Contract Act > Excell Erection, Inc., ARB No. 99-115 (ARB Sept. 29, 2000) |
Excell Erection, Inc., ARB No. 99-115 (ARB Sept. 29, 2000)
| U.S. Department of Labor | Administrative Review Board 200 Constitution Avenue, N.W. Washington, D.C. 20210 | ![]() |
ARB CASE NO. 99-115
DATE: September 29, 2000
In the Matter of:
EXCELL ERECTION, INC.
In re: Application of Wage Determination No.
VA930015 applied to sheet metal mechanics on
Contract No. N62470-89-C-9148 at Acute Care
Facility - Portsmouth Naval Hospital,
Portsmouth, Virginia.
Appearances:
For the Deputy Administrator:
For the Petitioner:
John J. Vermeire, III,
President,
Excell Erection, Inc., Gloucester, Virginia
U.S. Department of Labor, Washington, D.C.
The petitioner in this case, Excell Erection, Inc. (Excell), is a construction subcontractor performing work on an Acute Care Center at the Portsmouth Naval Hospital, Portsmouth, Virginia. The facility is being built pursuant to a contract with the U.S. Department of the Navy, Naval Facilities Engineering Command (Navy), and is subject to the Davis-Bacon Act, as amended, 40 U.S.C. §276a et seq. (1994). Excell is responsible for installing aluminum sheeting on the project's mansard roof, and aluminum roofing and siding on the project's rooftop mechanical room.
The wage determination applicable to the project did not include a sheetmetal worker job classification and wage rate. After the contract was awarded, Excell requested that a sheet metal worker classification be added through the Davis-Bacon conformance procedure found at 29 C.F.R. §5.5(a)(1)(v) (2000). After investigation, the Wage and Hour Administrator's designee (Administrator) concluded that the tasks to be performed by Excell's employees fell within the work jurisdiction of the ironworker job classification already contained in the applicable wage determination. The Administrator therefore denied the conformance request in a final decision letter issued July 14, 1999. This appeal followed.
We have jurisdiction pursuant to 29 C.F.R. §§7.1 and 7.9 (2000).
Late in 1993, the Navy awarded a construction contract to Centex Bateson Construction Company as the prime contractor on the Acute Care Center at the Portsmouth Naval Hospital, Contract No. N62470-89-C-9148. Administrative Record (AR) Tab O. The wage determination applicable to the project was WD VA91005, Mod. 3 (5/21/93). AR Tab P. This wage determination included a total wage/fringe rate of $20.10/hr. for the ironworker classification, but did not include a sheetmetal worker classification and rate. Id.
Excell was awarded a subcontract to perform roofing and siding work on the project. The scope of Excell's subcontract was described by the Navy as follows:
AR Tab E.
In December 1994, Centex Bateson submitted a conformance request to the Navy at Excell's request, asking that a "sheetmetal mechanic" classification be added to the wage determination at a total wage/fringe rate of $12.19/hr. The conformance request described the proposed sheetmetal mechanic's tasks as "installation of metal roofing, siding and insulation." AR Tab O. The Navy subsequently transmitted Excell's conformance request to the Wage and Hour Division with a recommendation that the additional classification not be approved by the Labor Department "since the duties described can be performed by a classification of employee (Ironworker) which is already contained in the applicable wage determination. . . ." Id.
Several months later, in July 1995, Centex Bateson submitted a slightly different conformance request to the Navy at the behest of another subcontractor on the project, Baker Roofing Company. Baker Roofing, which held the roofing subcontract, similarly asked that a sheetmetal mechanic classification be added to the wage determination at a $12.19/hr. rate; however, the tasks to be performed by this classification under Baker Roofing's conformance request were described as "installation of gutters, roof flashing, downspouts, facia, coping and all other related materials."2 AR Tab N. Like Excell's earlier request, this conformance request was transmitted to the Wage and Hour Division by the Navy. However, whereas the Navy had not recommended approval of Excell's proposed classification, the Navy affirmatively did recommend approval of Baker Roofing's proposal. Id.
Baker Roofing's request was approved promptly by the Wage and Hour Division (AR Tab M), but Excell's request was delayed while the Division investigated whether the tasks to be performed under Excell's subcontract might fall within the scope of the ironworker classification already found within the wage determination. On July 26, 1996, the Division advised the Navy's Contractor Labor Relations Advisor that it was denying Excell's conformance request "because the work to be performed by this [sheetmetal mechanic] classification may be performed by a classification already included in the wage determination[,]" citing 29 C.F.R. §5.5(a)(v)(A)(1). The Division's letter specifically noted that "[t]his matter is subject to further review if any interested party should wish to present additional information for consideration." AR Tab I.
Excell was notified of the Division's action and immediately notified Centex Bateson that it planned to seek further review. AR Tab H. Excell filed a letter with the Wage and Hour Division a month later in August 1996. AR Tab F. Excell's appeal to the Division prompted further inquiries to the Navy concerning the precise scope of the work within Excell's subcontract. AR Tab E.
It appears from the record that the Division took no formal action on Excell's conformance request until 1998. Apparently assuming that the Wage and Hour Division's July 1996 letter was dispositive of the conformance request, in April 1998 the Navy ordered Centex Bateson to withhold more than $43,000 from Excell for alleged underpayment of workers on the Acute Care Center project. AR Tab D.
According to Excell, it repeatedly contacted the Division's headquarters staff by telephone in an effort to obtain a final decision on the conformance request, without success. Finally, in October 1998 Excell contacted Congressman Herb Bateman of Newport News, Virginia, seeking his assistance with the matter. AR Tab C.
By letter dated July 14, 1999, addressed to Rep. Bateman, the Division issued a final decision denying the conformance request, thereby affirming the preliminary ruling that had been issued fully three years earlier in July 1996. Excell petitioned for review by this Board.
1. Whether the Administrator was correct in refusing to add the sheetmetal mechanic classification through the conformance mechanism because the tasks to be performed by the new classification were within the scope of a job classification already in the wage determination applicable to the project.
2. Whether the conformance should be granted because of the long period of time that Excell's request was pending before the Administrator.
The Board's review of decisions issued by the Administrator is in the nature of an appellate proceeding. 29 C.F.R. §7.1(e). We assess the Administrator's rulings to determine whether they are consistent with the statute and regulations, and are a reasonable exercise of the discretion delegated to the Administrator to implement and enforce the Davis-Bacon Act. Miami Elevator Co., ARB Case Nos. 98-086/97-145 , slip op. at 16 (Apr. 25, 2000), citing Dep't of the Army, ARB Case Nos. 98-120/121/122 (Dec. 22, 1999) (under the parallel prevailing wage statute applicable to federal service procurements, the Service Contract Act, 41 U.S.C. §351-358 (1994)).
The Davis-Bacon Act requires that laborers and mechanics employed on federal construction contracts be paid no less than the locally prevailing wage, as determined by the Secretary of Labor. 40 U.S.C. §276a. Contracting agencies incorporate prevailing wage determinations into bid packages and construction contracts. Through this process of predetermining the prevailing wage rates, all bidders for federal construction projects are provided with the same information concerning the minimum wage rates that must be paid on a federal construction procurement. 29 C.F.R. §5.5; see also 48 C.F.R. §36.213-(c)(1)(1999).
Although the primary objective of the Davis-Bacon Act is to protect local labor standards, the vehicle for achieving this end the Labor Department's determination of a prevailing wage schedule, and the incorporation of that wage schedule into construction project bid specifications and contracts also promotes fairness in the procurement system generally:
Pizzagalli Construction Co., ARB Case No. 98-090, slip op. at 5 (May 28, 1999).
The Davis-Bacon regulations include a mechanism for addressing errors, omissions or ambiguities that may exist in a wage determination: submitting a written request to the Administrator seeking reconsideration of the wage determination. 29 C.F.R. §1.8 (2000). However, challenges to a wage determination must be made prior to the award of a construction contract "to ensure that competing contractors know in advance of bidding what rates must be paid so that they may bid on an equal basis." See Kapetan Inc., WAB Case No. 87-33 (Sept. 2, 1988), and cases cited therein.
Under the Davis-Bacon regulations, the Wage and Hour Division may add an additional job classification and wage rate after the award of the construction contract through a procedure known as a conformance action. 29 C.F.R. §5.5(a)(1)(v). However, the procedure is designed to be very narrow in scope. The Administrator will add a new job classification through a conformance action only if it meets all the elements of this three-part test:
29 C.F.R. §5.5(a)(1)(v)(A).
In its Petition for Review, Excell lodges two major charges against the Administrator's August 1999 final decision letter: first, that the Administrator erred on the merits in refusing to add a sheetmetal mechanic classification; and second, that the conformed wage rate should be ordered by the Board because of the Administrator's lengthy delay in issuing the final decision letter. We consider each of these arguments in turn.
In its submissions to the Wage and Hour Division and this Board,
Excell makes several arguments in support of its conformance request. The company notes that
its work on the Acute Care Center involves affixing relatively thin (.040") aluminum
sheeting, using basic small tools such as hand snips, screw guns and drills. Although the
company acknowledges that this "preformed aluminum standing seam roofing and
siding" is attached to heavier metal elements that are erected by ironworkers, it argues that
the roofing and siding material is very different in character from the structural elements of the
mansard roof and mechanical penthouse structures and traditionally is installed by tradesmen
classified as sheetmetal workers. Excell contends that it has used a sheetmetal mechanic
classification for years to perform this work on many different Davis-Bacon jobs, all without
complaint by the government agencies involved.3 Excell supports its arguments with excerpts from the contract specifications from
the Acute Care Center project, as well as a letter from the manufacturer of the aluminum sheeting
product indicating that the material normally is installed by sheetmetal mechanics.
In addition, Excell notes that the Administrator ultimately added a
sheetmetal mechanic classification to the wage determination in 1995 in response to Baker
Roofing's conformance request. Excell observes that if it had learned about the Baker Roofing
conformance approval, it would not have pursued its separate request for the classification,
which Excell apparently views as identical.
While Excell's arguments are interesting, they miss the mark. In order to
add an additional job classification and wage rate through the conformance process, the proposed
classification must fall squarely within each element of the three-part conformance test,
supra. With specific regard to the first element of the test ("The work to be
performed by the classification is not performed by a classification in the wage
determination"), the Board has held that
U.S. Fire Protection, Inc., ARB Case Nos. 99-008, 039, slip op. at 5-6 (Aug. 30,
1999). In other words, when evaluating a proposed job classification under the expedited
conformance process, the Administrator is not required to reevaluate prevailing practices in the
area.
In this case, the Administrator correctly noted that the ironworker
classification in the wage determination was based on rates found in a collective bargaining
agreement. Pursuant to the Wage Appeals Board's decision in Fry Brothers Corp, WAB
Case No. 76-06 (June 14, 1977), the Administrator appropriately considered the jurisdictional
scope of the ironworker job classification in the collective bargaining agreement underlying the
wage rate. In his investigation into the conformance request, the Administrator contacted both
the Iron Workers and Sheet Metal Workers unions and determined that the particular tasks
contemplated under the Excell conformance request fell within the scope of duties that would
be performed by ironworkers under the collective bargaining agreement. This conclusion was
supported by communications from both unions, as well as evidence that ironworkers had
performed similar work previously in the locality (including correspondence from employers that
hired iron workers on similar projects).
Based on the materials in the Administrative Record, we are satisfied that
the Administrator's decision denying Excell's conformance request comports with the
requirements of the regulation and governing legal standards. The record plainly includes
sufficient evidence to conclude that the workers in the ironworker classification perform the
disputed work; thus, because there is a classification within the wage determination that can
perform these tasks, it would be inappropriate to add another classification through the
conformance process.
We also reject Excell's claim that it should have been allowed to use the
sheetmetal mechanic classification that was granted in response to the Baker Roofing
conformance request. The scope of work that was identified by Baker Roofing was very
specific: installation of gutters, roof flashing, downspouts, facia, coping and all other related
materials. There is no evidence in the record suggesting that these tasks are performed by
ironworkers or any other classification found in the wage determination; thus a conformance was
appropriate within the specific scope of the Baker Roofing request. However, as discussed
above, this cannot be said of the tasks required under Excell's subcontract. In this case, the two
requests are separate and distinct, and Excell is not entitled to rely on the sheetmetal mechanic
classification and wage rate granted to Baker Roofing.
In addition to challenging the merits of the Administrator's final decision,
Excell argues that it has been prejudiced by the extended period of time in which its request was
pending before the Administrator between 1996 and 1999, and that this Board therefore should
grant Excell's petition.
Nowhere in the record or in the Administrator's statement to this Board
is there any explanation for the lengthy delay by the Wage and Hour Division. In fact, it appears
that the Division was moved to act only after receiving an inquiry from a Member of Congress.
We do not condone such delay, and recognize Excell's frustration in this regard; but sympathy
alone does not provide a justification for granting a conformance request that plainly does not
meet the regulatory standard.
The Board considered a similar issue in another Davis-Bacon conformance
case, and concluded that the contractor (The Law Company) had not provided a sufficient
justification for overturning the Administrator's decision based on delay:
The Law Company, ARB Case No. 98-107, slip op. at 15-16 (Sept. 30, 1999).
As in The Law Company, we cannot conclude from the record
before us that Excell has been prejudiced by the delay in this case. Although the Wage and Hour
Division's actions have delayed the ultimate resolution of this dispute (i.e., a final
agency decision rejecting the conformance request, and the associated payment of back wages
to the affected employees), the net financial impact on Excell essentially is unchanged.
Arguably, the greater harm has been experienced by Excell's employees on the project, who have
been denied their full wages during this period. Accordingly, we find that Excell has not
demonstrated prejudice that would warrant reversing the Administrator's decision on this ground.
For the foregoing reasons, the decision of the Administrator is
AFFIRMED, and the Petition for Review is DENIED.
SO ORDERED.
PAUL GREENBERG
CYNTHIA L. ATTWOOD
1 This appeal has been assigned to a panel
of two Board members, as authorized by Secretary's Order 2-96. 61 Fed. Reg. 19,978 §5 (May
3, 1996).
2 In addition, Baker requested that
a "roofer" classification be added through the conformance process, because wage
determination WD VA91005, Mod. 3, did not include this job category.
3 Excell does not provide any
specific information about these other federal projects, such as their locations, the nature of the
construction element assembled, whether the sheetmetal mechanic classification was included in the
original wage determination or added through a conformance, the relative wage rates of the sheetmetal
mechanic and ironworker classifications, etc.
[Page 7]
[Page 8]
[Page 9]
[Page 10]
Chair
Member