| DOL Home > OALJ > Davis-Bacon Act/Service Contract Act > Hanford Atomic Metal Trades Council, ARB No. 99-009 (ARB Nov. 25, 1998) |
ARB CASE NO. 99-009
(Formerly ARB Case No. 98-138)
DATE: November 25, 1998
In the Matter of:
HANFORD ATOMIC METAL TRADES
COUNCIL
In re: Wage Determination for Project
W-211, The Department of Energy
Operations Office, Richland, WA.
BEFORE: THE ADMINISTRATIVE REVIEW BOARD
By motion dated November 12, 1998, Petitioner Hanford Atomic Metal Trades Council has submitted a Notice of Withdrawal of Motion for Summary Reversal and Appeal. We treat the filing as a motion to dismiss.
In the Notice and its attachment, Petitioner indicates that it does not at this time seek an adjudication of the Acting Administrator's final ruling letter dated October 23, 1998, but instead has requested additional reconsideration directly from the Acting Administrator. Petitioner requests dismissal of its petition without prejudice.1
For good cause shown, the Petitioner's motion is GRANTED, and this petition is dismissed without prejudice.
SO ORDERED.
PAUL
GREENBERG
Chair
CYNTHIA L.
ATTWOOD
Acting Member
1 We note that the Secretary's regulations governing practice before the Board with regard to federal service contracts specifically provide that an aggrieved party must submit a petition for review of a final decision of the Administrator within 60 days of the decision's date. 29 C.F.R. §8.7(b) (1998).